Just a short note to say that if it's quiet around here, it's because our internet is still a little sketchy. Sometimes it works, sometimes it doesn't. But I think about all of you often, andIi miss checking in here and on your blogs. Hopefully in October I'll be back here regularly. We do have a tentative move-in date - and a schedule for getting there.
This is what our schedule looks like ::
September
8-11 have the ceiling ready for insulation and insulate the gable ends
11-12 gable end interiors finished
13-15 finish the soffit and facia
16-18 finish the walk-out front and the exterior trim
19 put up the last 10 courses of ship-lap on the ceiling
20-24 paint and trim the interior
25-26 stairs, ladder and countertops
27-30 clean, clean, clean
October 2-3 MOVE IN!
To all of you have been praying for and thinking of us, thank you. Thank you so much. So very much. And please keep praying as you think of us. God is so good to answer our prayers. We will arrive at an answer for the final mortgage in God's timing. For now we are exhausting our options and waiting on Him.
I'll be back as soon as I can, my friends.
Love, ~e